Fine-Slicing Beats Estimation for Predictability

As requested by JB in the comments to my previous post, here is some data about what happens when a team choose fine-slicing over estimation.

You’re about to see a CFD chart drawn by a team who used BDD to break down every requirement into scenarios before they started hacking on them. The items on the left aren’t actually scenarios in this case, they’re very small user stories which tended to be of a size of about 3-4 scenarios each. The point is, we broke everything down into the smallest pieces of behaviour we could, then re-assembled them into chunks that were meaningful enough to build together.

Rather than using story points to manage the variation in size of stories, we gave each story a value of one point, and used BDD analysis to try to ensure each story was a uniformly small size.

This data was collected over a period of about six months by a team of about eight developers. Their system (a high-volume website) was already live and they were adding features to it.

What strikes me the most is how straight the ‘done’ line is.

Who Needs Estimates

Agile / Lean Software Development

Comments (0)

Permalink

Using BDD Scenarios to Track Project Velocity

Before you write any code, start by brainstorming all the scenarios you’ll need to cover to make the story done. Do this collaboratively with everyone (devs, testers, UX, business people, product owner) who is interested in the story. Don’t try to make them valid Cucumber scenarios, just make a list of them on a whiteboard, index cards, or in a text file.

Now look at all the scenarios you have. Does the product owner really want you to build the product to satisfy all of them? Can you cut any out and defer them as another story to build later? Can you drop any of them altogether? Get rid of as many as you can until the story is as small as you can make it.

Now count how many scenarios you have left, and write that number on the story card. At the end of the iteration, count up how many scenarios you’re managed to deliver in total across all the stories you’ve done, and start using that as your velocity metric. It’s much, much more accurate in my experience than estimated story points. What’s more, the process of exploring the scenarios means you can agree a clear scope for the story before you get started.

Teams who are doing this well are getting things done much more quickly than they did before. Not only do they build a suite of automated regression tests, but they waste a lot less time writing the wrong code because of misunderstood requirements.

Agile / Lean Software Development

Comments (5)

Permalink

The Real Point of Planning Poker

It’s funny, you’d think, from reading about planning poker that the purpose of this exercise is to come up with accurate estimates. I think that’s missing the point.

The estimates are a useful by-product, if your organisation values such things, but actually the most important benefit you get from planning poker is the conversation. As part of the exercise, you explore the story as a team, and uncover any misunderstandings about the scope and depth of the work to be done to satisfy the story. The result of this exploration is a shared understanding of what the story means.

There are other ways to have this same conversation. My favoured practice is to hold a specification workshop where the team explores the scenarios that a user could encounter when using this new functionality. These scenarios are a much more useful product, to me, than an estimate. They give me a starting point for writing my automated acceptance tests, and they also give us all a concrete reference point as to the scope of the story. If my organisation needs estimates to be happy, we can count the number of scenarios to give a realistic feel for the relative size of the story.